Construction Parameters Control of Shield Tunnel Underneath Traversing Existing Dual Shield Tunnels
-
摘要: 为研究盾构下穿既有盾构隧道时施工参数的合理取值,以北京南水北调东干渠工程盾构隧道穿越既有地铁盾构隧道施工为依托,通过对既有隧道沉降的数值模拟和现场监测数据、盾构施工参数的分析,讨论了既有左右线隧道沉降存在差异的原因,总结了控制沉降的施工参数经验,阐述了既有隧道受穿越施工扰动的沉降规律,提出并验证了盾构隧道病害整治的方法.研究结果表明:受盾构施工参数的影响,既有左线隧道沉降23.9 mm,而右线仅沉降4.8 mm,沉降差异明显,但规律基本一致;盾构施工时,土仓压力调整级差不宜大于0.005 MPa,严格控制同步注浆压力在0.50 MPa,二次补浆压力在0.20~0.35 MPa,曲线段适当减缓掘进速度;已投入运营的地铁维修作业时间短,宜通过化学注浆治理管片接缝和螺栓孔处的渗漏水,压力注胶充填树脂治理道床裂缝.Abstract: In order to investigate reasonable construction parameters of a shield tunnel underneath traversing existing dual shield tunnels, the project that shield tunnel of the East Trunk Canal of the South-to-North Water Diversion Project traversed subway shield tunnels in Beijing was studied as an example. The reason for the difference in settlement between the left and right tunnels was determined by analyzing the numerical simulation and in situ monitoring data of the settlement of existing tunnels and the shield construction parameters. Then, the construction parameters for controlling settlement were given. Moreover, the trends in the variation in settlement of existing tunnels caused by traversing construction was discussed and some measures to counter shield tunnel diseases were proposed and verified. The results show that because of the influences of shield construction with different parameters, the final settlement of the existing left tunnel is 23.9 mm, while that of the right tunnel is only 4.8 mm. Although the settlements of the two tunnels differ significantly, their trends in variation are almost consistent. During the construction, the adjusted range of the working chamber pressure should not be more than 0.005 MPa and the synchronous grouting pressure should be adjusted accurately to be 0.50 MPa. Meanwhile, the secondary grouting pressure should be 0.20-0.35 MPa, and the tunneling speed in the curve section is required to slow down appropriately. Since the maintenance time in a subway is short, chemical grouting is adopted to solve the problem of leakage of water in segment joints and bolt holes while a pressure filling resin is used to repair the cracks in the slab.
-
表 1 土层参数
Table 1. Soil parameters
土层名称 厚度/m 密度/(kg·m-3) 压缩模量/MPa 泊松比 黏聚力/kPa 摩擦角/(°) ①填土 2 1 800 32.7 — 8 10 ③粉质黏土 5 1 990 7.0 0.40 28 12 ③1粉土 4 1 870 7.0 0.35 20 24 ⑤粉质黏土 6 2 000 8.0 0.34 30 15 ⑥1卵砾石 13 2 100 40.0 0.32 — 32 ⑦粉质黏土 6 1 950 12.0 0.42 50 18 ⑧卵石 4 2 200 42.0 0.35 — 35 ⑨粉质黏土 11 1 900 11.0 0.35 48 17 表 2 盾构结构参数
Table 2. Shield structure parameters
名称 厚度/m 弹性模量/
MPa泊松比 密度/
(kg·m-3)盾构管片(C50) 0.30 34.50×103 0.20 2 500 盾壳(钢材) 0.07 212.00×103 0.31 7 850 流动等代层 0.06 0.75 0.35 2 000 初凝等代层 0.06 1.50 0.25 2 300 表 3 模拟内容
Table 3. Simulation contents
步序 模拟内容 n “杀死”隧道范围内的土体单元, 在掌子面处施加土仓压力, “激活”等代层单元, 其参数为盾壳参数. n-1、n-2 等代层单元参数保持为盾壳参数. n-3~n-5 在第n-5步等代层单元后端施加向前的千斤顶推力; “激活”管片单元, 其中,在第n-3步管片单元前端施加向后的千斤顶推力. n-6 “杀死”等代层单元, 延径向施加注浆压力. n-7 “激活”等代层单元, 其参数为流动等代层参数. n-8 等代层单元参数更改为初凝等代层参数. 表 4 盾构掘进至不同位置时既有隧道沉降值
Table 4. Settlement of existing tunnels when shield tunnels to different locations
mm 既有隧道 747环 756环 767环 768环 盾尾脱离左线外缘 779环 790环 盾尾脱离右线外缘 沉降稳定 左线 -2.2 -10.6 -18.5 -18.8 -19.7 -21.3 -21.9 — -23.9 右线 -0.1 -0.1 -0.2 -0.4 — -1.6 -1.8 -3.9 -4.8 -
PECK R B. Deep excavation and tunnelling in soft ground[R]. Mexico: Proceedings of 7th International Conference on Soil Mechanics and Foundation Engineering, 1969. 康庄, 宫全美, 何超.基于盾构隧道斜交下穿的修正Peck公式法[J].同济大学学报:自然科学版, 2014, 42(10):1562-1566. http://d.old.wanfangdata.com.cn/Periodical/tjdxxb201410016KANG Zhuang, GONG Quanmei, HE Chao. Modified peck equation method for shield tunnel oblique crossing upper railway[J]. Journal of Tongji University:Natural Science, 2014, 42(10):1562-1566. http://d.old.wanfangdata.com.cn/Periodical/tjdxxb201410016 廖少明, 杨俊龙, 奚程磊, 等.盾构近距离穿越施工的工作面土压力研究[J].岩土力学, 2005, 26(11):1727-1730. doi: 10.3969/j.issn.1000-7598.2005.11.006LIAO Shaoming, YANG Junlong, XI Chenglei, et al. Approach to earth balance pressure of shield tunneling across ultra-near metro tunnel in operation[J]. Rock and Soil Mechanics, 2005, 26(11):1727-1730. doi: 10.3969/j.issn.1000-7598.2005.11.006 何川, 苏宗贤, 曾东洋.地铁盾构隧道重叠下穿施工对上方已建隧道的影响[J].土木工程学报, 2008, 41(3):91-98. doi: 10.3321/j.issn:1000-131X.2008.03.015HE Chuan, SU Zongxian, ZENG Dongyang. Influence of metro shield tunneling on existing tunnel directly above[J]. China Civil Engineering Journal, 2008, 41(3):91-98. doi: 10.3321/j.issn:1000-131X.2008.03.015 MARSHALL A M, KLAR A, MAIR R J. Tunneling beneath buried pipes:view of soil strain and its effect on pipeline behavior[J]. Journal of Geotechnical and Geoenvironmental Engineering, 2010, 136(12):1664-1672. doi: 10.1061/(ASCE)GT.1943-5606.0000390 廖少明, 杨宇恒.盾构上下夹穿运营地铁的变形控制与实测分析[J].岩土工程学报, 2012, 34(5):812-818. http://www.wanfangdata.com.cn/details/detail.do?_type=perio&id=QK201201674623LIAO Shaoming, YANG Yuheng. Deformation analysis and control of a running subway crossed by upper-and lower-shield in succession[J]. Chinese Journal of Geotechnical Engineering, 2012, 34(5):812-818. http://www.wanfangdata.com.cn/details/detail.do?_type=perio&id=QK201201674623 刘树佳, 张孟喜, 吴惠明, 等.新建盾构隧道上穿对既有隧道的变形影响分析[J].岩土力学, 2013, 34(增刊1):399-405. http://d.old.wanfangdata.com.cn/Conference/8209169LIU Shujia, ZHANG Mengxi, WU Huiming, et al. Deformation effect on existing tunnels overlapped by new tunnel in lower-region[J]. Rock and Soil Mechanics, 2013, 34(Sup.1):399-405. http://d.old.wanfangdata.com.cn/Conference/8209169 李磊, 张孟喜, 吴惠明, 等.近距离多线叠交盾构施工对既有隧道变形的影响研究[J].岩土工程学报, 2014, 36(6):1036-1043. http://d.old.wanfangdata.com.cn/Periodical/ytgcxb201406009LI Lei, ZHANG Mengxi, WU Huiming, et al. Influence of short-distance multi-line overlapped shield tunnelling on deformation of existing tunnels[J]. Chinese Journal of Geotechnical Engineering, 2014, 36(6):1036-1043. http://d.old.wanfangdata.com.cn/Periodical/ytgcxb201406009 朱春雷.盾构斜向下穿运营隧道的水平位移影响分析[J].都市快轨交通, 2016, 29(2):61-65, 70. doi: 10.3969/j.issn.1672-6073.2016.02.014ZHU Chunlei. Analysis on horizontal displacement of subway in operation caused by oblique-downward shield[J]. Urban Rapid Rail Transit, 2016, 29(2):61-65, 70. doi: 10.3969/j.issn.1672-6073.2016.02.014 张琼方, 夏唐代, 丁智, 等.盾构近距离下穿对已建地铁隧道的位移影响及施工控制[J].岩土力学, 2016, 37(12):3561-3568. http://d.old.wanfangdata.com.cn/Periodical/ytlx201612027ZHANG Qiongfang, XIA Tangdai, DING Zhi, et al. Effect of nearby undercrossing tunneling on the deformation of existing metro tunnel and construction control[J]. Rock and Soil Mechanics, 2016, 37(12):3561-3568. http://d.old.wanfangdata.com.cn/Periodical/ytlx201612027 朱蕾, 赵敬妍.盾构近距离下穿对上覆已建隧道影响的实测研究[J].地下空间与工程学报, 2014, 10(3):656-662. http://d.old.wanfangdata.com.cn/Periodical/dxkj201403026ZHU Lei, ZHAO Jingyan. Monitoring data analysis of shield-driven construction undercrossing the existing tunnel in a short distance[J]. Chinese Journal of Underground Space and Engineering, 2014, 10(3):656-662. http://d.old.wanfangdata.com.cn/Periodical/dxkj201403026 黄宏伟, 徐凌, 严佳梁, 等.盾构隧道横向刚度有效率研究[J].岩土工程学报, 2006, 28(1):11-18. doi: 10.3321/j.issn:1000-4548.2006.01.002HUANG Hongwei, XU Ling, YAN Jialiang, et al. Study on transverse effective rigidity ratio of shield tunnels[J]. Chinese Journal of Geotechnical Engineering, 2006, 28(1):11-18. doi: 10.3321/j.issn:1000-4548.2006.01.002 张云, 殷宗泽, 徐永福.盾构法隧道引起的地表变形分析[J].岩石力学与工程学报, 2002, 21(3):388-392. doi: 10.3321/j.issn:1000-6915.2002.03.019ZHANG Yun, YIN Zongze, YU Yongfu. Analysis on three-dimensional ground surface deformations due to shield tunnel[J]. Chinese Journal of Rock Mechanics and Engineering, 2002, 21(3):388-392. doi: 10.3321/j.issn:1000-6915.2002.03.019 张宏洲, 张金伟, 翟建华.盾构法隧道等代层参数反演的ANSYS方法[J].隧道建设, 2006, 26(5):8-10. doi: 10.3969/j.issn.1672-741X.2006.05.003ZHANG Hongzhou, ZHANG Jinwei, ZHAI Jianhua. Ansys method for deduction of parameters of equivalent circular zone of shield tunnel[J]. Tunnel Construction, 2006, 26(5):8-10. doi: 10.3969/j.issn.1672-741X.2006.05.003 张飞进, 高文学.盾构隧道沉降影响因素分析与施工优化[J].北京工业大学学报, 2009, 35(5):621-625. http://www.wanfangdata.com.cn/details/detail.do?_type=perio&id=SciencePaper201303040000059364ZHANG Feijin, GAO Wenxue. Shield tunnel subsidence influence factor analysis and construction optimization[J]. Journal of Beijing University of Technology, 2009, 35(5):621-625. http://www.wanfangdata.com.cn/details/detail.do?_type=perio&id=SciencePaper201303040000059364 朱才辉, 李宁, 柳厚祥, 等.盾构施工工艺诱发地表沉降规律浅析[J].岩土力学, 2011, 32(1):158-164. doi: 10.3969/j.issn.1000-7598.2011.01.026ZHU Caihui, LI Ning, LIU Houxiang, et al. Analysis of ground settlement induced by workmanship of shield tunneling[J]. Rock and Soil Mechanics, 2011, 32(1):158-164. doi: 10.3969/j.issn.1000-7598.2011.01.026 袁小会, 韩月旺, 钟小春.盾构隧道壁后注浆压力分布模型[J].西南交通大学学报, 2011, 46(1):18-23. doi: 10.3969/j.issn.0258-2724.2011.01.003YUAN Xiaohui, HAN Yuewang, ZHONG Xiaochun. Pressure distribution model of simultaneous backfill grouting of shield tunnel[J]. Journal of Southwest Jiaotong University, 2011, 46(1):18-23. doi: 10.3969/j.issn.0258-2724.2011.01.003 陈馈, 洪开荣, 吴学松.盾构施工技术[M].北京:人民交通出版社, 2016:167. 倪克琦, 叶利宾, 张军, 等. QB(J)/BDY(A)XL003-2015北京市地铁运营有限公司企业标准技术标准工务维修规则[S].北京: 北京市地铁运营有限公司, 2015.