Simulation of Construction Process of Loukouni Bridge in the Republic of Congo
-
摘要: Loukouni桥是刚果(布)1号公路Ⅱ期工程中的一座采用缆索吊装的上承式钢箱拱桥,为保证其施工过程的安全性,用零弯矩法、零位移法和定长扣索法,分别获得了施工过程中扣索索力和拱肋预抬值,并利用通用有限元软件ANSYS的生死单元功能对施工过程进行了仿真分析.计算结果表明:定长扣索法和零位移法确定的施工方案均能满足拱肋线形、施工截面应力和变形控制的要求,定长扣索法更优,可以作为该桥施工首选的设计方案;试算零位移法是确定施工扣索索力的一种简便有效的方法.Abstract: Loukouni bridge is a deck type arch bridge with box section and is a part of the second stage of the first national road project of the Republic of Congo. This bridge will be constructed with cable erecting equipment. To make sure its construction safety, three methods, including the zero moment method, the zero displacement method and the invariable cable method, were used to calculate the cable force of fastening cable and the pre-camber of main arch during the construction. Live and dead elements provided by the general FE (finite element) software ANSYS were utilized to simulate the construction of the bridge. The research result shows that both the zero displacement method and the invariable cable method can meet the construction demand in terms of the shape of the arch, the stress of arch section and the deformation of the arch. In the two methods, the invariable cable method is better and should be the first choice applied to the Loukouni bridge. The trial zero displacement method is a simple and effective way to obtain the cable force.
-
田仲初. 大跨度钢箱拱桥的施工控制关键技术与动力特性研究. 长沙:中南大学土木建筑学院, 2007. 陈彦江, 付玉辉, 孙航. 灰色理论在钢管混凝土拱桥施工控制中的应用[J]. 哈尔滨工业大学学报, 2007, 39(4): 546-548. CHEN Yanjiang, FU Yuhui, SUN Hang. Application of grey system method in construction control of long-span concrete-filled steel-tube arch bridge[J]. Journal of Harbin Institute of Technology, 2007, 39(4): 546-548. 张治成, 叶贵如, 王云峰. 大跨度拱桥拱肋线形调整中的扣索索力优化[J]. 工程力学, 2004, 21(6): 187-192. ZHANG Zhicheng, YE Guiru, WANG Yunfeng. Optimization of stayed-buckle cable forces during adjustment of the line-shape on long span bridge[J]. Engineering Mechanics, 2004, 21(6): 187-192. HE Xiongjun, SHEN Chenwu, CHEN Qiaosheng, et al. Adjustment of buckle-cable forces under cable hoisting construction of concrete-filled steel tubular arch bridges[J]. Journal of Wuhan Transportation University, 1999, 23(5): 575-578. AU F T K, WANG J J, LIU G D. Construction control of reinforced concrete arch bridges[J]. Journal of Bridge Engineering, 2002, 8(1): 39-45. GRANATA M F, MARGIOTTA P, RECUPERO A, et al. Partial elastic scheme method in cantilever construction of concrete arch bridges[J]. Journal of Bridge Engineering, 2013, 18(7): 663-672. 王小成. 大跨度钢管混凝土拱桥拱肋吊装施工过程空间仿真计算. 武汉:武汉理工大学土木工程与建筑学院, 2006. DIMANDE A, PIMENTEL M, FLIX C, et al. Monitoring system for execution control applied to a steel arch footbridge[J]. Structure and Infrastructure Engineering, 2012, 8(3): 277-294. 田仲初, 陈得良, 颜东煌, 等. 钢箱提篮拱桥施工控制的关键技术研究[J]. 中国公路学报, 2004, 17(3): 46-50. TIAN Zhongchu, CHEN Deliang, YAN Donghuang, et al. Study of key technology with construction control of steel box basket-handling arch bridge[J]. China Journal of Highway and Transport, 2004, 17(3): 46-50. 王元清, 宗亮, 张龙英, 等. 考虑中欧规范差异的刚果(布)Loukouni大桥设计复核分析[J]. 铁道科学与工程学报, 2012, 9(5): 1-6. WANG Yuanqing, ZONG Liang, ZHANG Longying, et al. Design review on Loukouni bridge in the Republic of Congo considering the difference between Chinese code and Eurocode[J]. Journal of Railway Science and Engineering, 2012, 9(5): 1-6. 中交第一公路工程局有限公司. JTG/T F502011 公路桥涵施工技术规范[S]. 北京:人民交通出版社, 2011. REDDY P, JAMSHID G, NEIL M H. Simulation of construction of cable-stayed bridges[J]. Journal of Bridge Engineering, 1999, 4(4): 249-257. TIAN Weifeng, ZHANG Liangliang, AYAD T S. Calculation of cable force and pre-camber for long-span rib arch bridge construction by unstressed state control method//Third International Conference on Trans-portation Engineering. Chengdu: ASCE, 2011: 2104-2109. 李顺国. 大跨度钢管混凝土拱桥拱肋吊装过程几何非线性分析. 武汉:武汉理工大学土木工程与建筑学院, 2002. 王新敏. ANSYS工程结构数值分析[M]. 北京:人民交通出版社, 2007: 291-293.
点击查看大图
计量
- 文章访问数: 992
- HTML全文浏览量: 89
- PDF下载量: 571
- 被引次数: 0