Based on a field test and FEM( finite elementmethod) numerical simulation, the load-
bearingmechanism of the tunnelanchorage system ofsuspension bridgeswith pre-stressed anchor cable
was investigated. The key parameters were determined through the back-analysis of the dynamic
construction process. In the numerical simulation, interactions between anchorage and rockmass and
between anchor cable, grout and rockmasswere simulated with zero-thickness contact elements. The
research indicates that the initial pre-stress and free length of anchor cable determine the loads
participated by anchor cable and anchorage on the tunnel anchorage system and their load-bearing
occasion. There exists a least free length ofanchor cable to form a new confining pressure effect—rock
anchoredwall to transfer and distribute stresses uniformly in rockmass.