With 2-D finite element method (FEM), the moment and displacement of metope piles,
the stress and displacement of interface between anchorage pile and surrounding rock, the settlement
and earth pressure of filling soil, and the internal force of anchored cables are calculated in six typical
conditions of construction. And the calculation results accord basically with those of field observation
and other numerical methods. The results show that the the moment and displacement of metope
piles can be decreased effectively by the use of prestressed cables.