Citation: | ZHONG Xiaochun, HUANG Siyuan, ZHU Weibin, CHEN Qiaosong, YOU Zhi. Analysis of Sealing Performance of Shield Tail Brush Based on Compression and Grease Escape Test[J]. Journal of Southwest Jiaotong University, 2023, 58(1): 125-132. doi: 10.3969/j.issn.0258-2724.20210814 |
In order to study the effect of the quality of shield tail brush on the working performance of shield tail sealing system, based on dynamic compression test and grease escape test, the influence mechanism of long-term extrusion, wear degree of shield tail brush and mortar penetration on sealing performance of shield tail brush are revealed. Firstly, the variation law of the adhesion force of shield tail brush under various influencing factors is discussed based on the dynamic compression test. Secondly, the grease escape volume of shield tail brush under different working conditions is obtained by grease escape test. Finally, taking the adhesion force as the medium, the factors affecting the quality of shield tail brush are connected with the volume of grease escape, and the sealing performance of shield tail brush is discussed. The results show that, long-term extrusion, wear degree of shield tail brush and mortar penetration ratio have significant effects on the elastic properties of shield tail brush, especially the mortar penetration ratio can cause the elastic property loss up to 90%. There is a critical pressure in the grease pressure, and the critical grease pressure with shield tail clearance of 50, 70, 90 mm is 0.4, 0.3, 0.2 MPa respectively. When grease pressure is lower than the critical pressure, the volume of grease escape is very small. When it exceeds the critical pressure, the volume of grease escape increases sharply. The grease pressure further increases by 0.1 MPa, the volume of grease escape increases by more than 4 times. Under the condition of average shield tail clearance (70 mm), the volume of grease escape exceeds the allowable upper limit when the wear of protective plate exceeds 1/2 and the mortar penetration ratio exceeds 10%.
[1] |
崔玖江. 盾构隧道施工风险与规避对策[J]. 隧道建设,2009,29(4): 377-396.
CUI Jiujiang. Risks and countermeasures for construction of shield-bored tunnels[J]. Tunnel Construction, 2009, 29(4): 377-396.
|
[2] |
潘国庆. 隧道施工中盾构盾尾密封渗漏风险源分析[J]. 中国市政工程,2008(5): 59-60,93.
PAN Guoqing. Analysis of risk sources in seal leakage at shield tail during tunneling[J]. China Municipal Engineering, 2008(5): 59-60,93.
|
[3] |
KAWASAKI M, YOSHIZAKI K, SUGIMOTO M. Water sealing by wire brush with grease for pneumatic caisson method at great depth underground[J]. Geotechnical Engineering, 2017, 48(2): 64-71.
|
[4] |
任广艳. 透水涌砂冒险堵漏隧道坍塌撤人不及: 广东省佛山市轨道交通2号线“2·7”透水坍塌重大事故分析[J]. 吉林劳动保护,2019(8): 40-42.
|
[5] |
李奕,钟志全. 一种新型盾尾刷的设计与应用[J]. 建筑机械化,2011,32(1): 82-84. doi: 10.3969/j.issn.1001-1366.2011.01.020
LI Yi, ZHONG Zhiquan. Design and application of a new type of shield tail brush[J]. Construction Mechanization, 2011, 32(1): 82-84. doi: 10.3969/j.issn.1001-1366.2011.01.020
|
[6] |
霍志光. 新型盾尾刷设计与应用分析[J]. 价值工程,2011,30(8): 87-88.
HUO Zhiguang. Design and application analysis of new shield tail brush[J]. Value Engineering, 2011, 30(8): 87-88.
|
[7] |
沈桂丽,刘金祥,李剑雄,等. 盾尾密封刷实验平台的设计与研究[J]. 隧道建设,2015,35(8): 851-854.
SHEN Guili, LIU Jinxiang, LI Jianxiong, et al. Design of and study on tail brush experimental platform[J]. Tunnel Construction, 2015, 35(8): 851-854.
|
[8] |
李大伟,刘金祥,赵新合. 盾尾刷综合实验平台的研制[J]. 建筑机械化,2015,36(2): 70-72.
LI Dawei, LIU Jinxiang, ZHAO Xinhe. Development of tail sealing brushes comprehensive testing bench[J]. Construction Mechanization, 2015, 36(2): 70-72.
|
[9] |
MAIDL B, HERRENKNECHT M, MAIDL U, et al. Mechanised shield tunnelling[M]. 2nd ed. Berlin: Ernst and Sohn, 2012: 87-99.
|
[10] |
魏林春. 盾尾钢丝刷受力性能模拟试验研究[J]. 隧道建设(中英文),2021,41(2): 206-211.
WEI Linchun. Experimental study on mechanical bahavior of wire brushes on shield tail[J]. Tunnel Construction, 2021, 41(2): 206-211.
|
[11] |
LI F, YANG Y Y, TAO M J, et al. A cement paste-tail sealant interface modified with a silane coupling agent for enhancing waterproofing performance in a concrete lining system[J]. RSC Advances, 2019, 9(13): 7165-7175. doi: 10.1039/C8RA10457C
|
[12] |
李光,王宁. 基于多相流数值模拟的盾尾密封系统密封性研究[J]. 隧道建设(中英文),2021,41(增1): 490-496.
LI Guang, WANG Ning. Sealing performance of shield tail sealing system based on multiphase flow numerical simulation[J]. Tunnel Construction, 2021, 41(S1): 490-496.
|
[13] |
钭婧. 盾构机盾尾密封系统压力分布特性研究[D]. 大连: 大连理工大学, 2021.
|